1Opinion of the CourtDupont, J.

The plaintiff and the defendant entered into a written contract which provided that the plaintiff was to perform electrical work on premises owned by the defendant. The agreement provided that full payment was to be made upon completion of the work, although the agreement did not specify any particular time for completion.

When the defendant failed to pay the plaintiff the balance of the sum due under the contract upon the alleged completion of the plaintiff’s work, the plaintiff gave written notice to the defendant of its intent to file a mechanic’s lien. Such a lien was filed and suit was…

2Cases cited6 opinions

  1. Pandolphe's Auto Parts, Inc. v. Town of ManchesterSupreme Court of Connecticut · 1980
  2. Kaplan v. KaplanSupreme Court of Connecticut · 1982
  3. Appliances, Inc. v. YostSupreme Court of Connecticut · 1982
  4. Cohn v. DunnSupreme Court of Connecticut · 1930
  5. Scoville v. ScovilleSupreme Court of Connecticut · 1979

1 more not listed; retrieve them via the Exa API.

3Cited by12 opinions

  1. Red Rooster Construction Co. v. River Associates, Inc.Supreme Court of Connecticut · 1993
  2. Anderson v. Town of LitchfieldConnecticut Appellate Court · 1985
  3. Archambault v. WadlowConnecticut Appellate Court · 1991
  4. Burkert v. Petrol Plus of Naugatuck, Inc.Connecticut Appellate Court · 1985
  5. State v. ColonConnecticut Appellate Court · 1995

7 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API