Austin Engineering Co. v. United States
United States Court of Claims
1Opinion of the CourtWilliams, Judge
This suit was brought by plaintiff June 27, 1936, to recover $55,039.82 for certain alleged extra costs and expenses arising from certain alleged extra work which, it is alleged, the defendant required plaintiff to perform for which no payment was made by the defendant under the contract and, also, for penalties for delay alleged to have been erroneously imposed and collected by the defendant.
The case is now before the court upon defendant’s plea to the jurisdiction under which the defendant contends that the claim accrued May 25, 1929, when construction of the buildings called for by the…
2Cases cited6 opinions
- United States v. WurtsSupreme Court of the United States · 1938
- Borer v. ChapmanSupreme Court of the United States · 1887
- Utah Power & Light Co. v. United StatesUnited States Court of Claims · 1929
- Smith Courtney Co. v. United StatesUnited States Court of Claims · 1911
- Penn Bridge Co. v. United StatesUnited States Court of Claims · 1930
1 more not listed; retrieve them via the Exa API.
3Cited by18 opinions
- Crown Coat Front Co. v. United StatesSupreme Court of the United States · 1967
- Nager Electric Company, Inc. And Keystone Engineering Corporation v. The United StatesUnited States Court of Claims · 1966
- Oceanic Steamship Co. v. United StatesUnited States Court of Claims · 1964
- Lins v. United StatesUnited States Court of Claims · 1982
- Mitchell v. United StatesUnited States Court of Claims · 1986
13 more not listed; retrieve them via the Exa API.