Griffiths v. United States
United States Court of Claims
1Opinion of the CourtWilliams, Judge
This case grows out of a contract entered into between the plaintiff and the War Department for the construction of ten lavatory buildings at Fort Sheridan, Illinois.
The plaintiff seeks recovery on three items, viz:(1) The sum of $2,440, imposed and deducted as liquidated damages because of 122 days’ delay in completing the work under the contract.(2) The sum of $7,778.00, alleged loss and damage because of defendant’s requirement that plumbing fixtures manufactured by J. L. Mott Company, Inc., be installed instead of Armco plumbing fixtures which plaintiff claims met the requirements of the…
2Cases cited1 opinion
- Monroe v. United StatesSupreme Court of the United States · 1902
3Cited by9 opinions
- The Len Company and Associates v. The United StatesUnited States Court of Claims · 1967
- W. H. Armstrong & Co. v. United StatesUnited States Court of Claims · 1943
- Karno-Smith Co. v. United StatesUnited States Court of Claims · 1936
- Hirsch v. United StatesUnited States Court of Claims · 1941
- Holmberg v. United StatesUnited States Court of Claims · 1940
4 more not listed; retrieve them via the Exa API.