1Opinion of the CourtWhaley, Judge

The plaintiff on September 12, 1931, entered into a contract with the defendant by which the plaintiff agreed to furnish all labor and materials and to perform all work required for the construction of the United States Post Office Building and Court House at Trenton, New Jersey, except elevators and foundations, for the sum of $749,500 according to specifications, schedules, and drawings which were made a part of the contract. The building was to be completed within 480 calendar days after the date of receipt of the notice to proceed. On September 24,1931, the plaintiff was notified to…

2Cases cited6 opinions

  1. United States v. SmithSupreme Court of the United States · 1877
  2. Suburban Contracting Co. v. United StatesUnited States Court of Claims · 1932
  3. Griffiths v. United StatesUnited States Court of Claims · 1933
  4. Goldstone v. United StatesUnited States Court of Claims · 1925
  5. Edge Moor Iron Co. v. United StatesUnited States Court of Claims · 1925

1 more not listed; retrieve them via the Exa API.

3Cited by14 opinions

  1. George A. Fuller Co. v. United StatesUnited States Court of Claims · 1947
  2. Stein Bros. Mfg. Co. v. United StatesUnited States Court of Claims · 1963
  3. New York Shipbuilding Corporation v. The United StatesUnited States Court of Claims · 1967
  4. CLIMATIC RAINWEAR, CO. v. United StatesUnited States Court of Claims · 1950
  5. John A. Johnson & Sons, Inc. v. United StatesUnited States Court of Claims · 1967

9 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API