L. Harvey Concrete, Inc. v. Agro Construction & Supply Co.
Court of Appeals of Arizona
1Opinion of the Court
OPINION
PATTERSON, Judge.
In this appeal we must determine whether a particular “pay-when-paid” provision in an agreement between a contractor and subcontractor is effective as a condition precedent to excuse the contractor from paying the subcontractor where a corresponding payment was not received by the contractor from the owner. The trial court granted summary judgment for the contractor, concluding as a matter of law that the language created a condition precedent and that the condition had not been satisfied. For the reasons explained herein, we agree with the trial court that a condition…
2Cases cited9 opinions
- Orme School v. ReevesArizona Supreme Court · 1990
- The Thos. J. Dyer Company v. Bishop International Engineering Company and General Insurance Company of AmericaCourt of Appeals for the Sixth Circuit · 1962
- Pioneer Roofing Co. v. Mardian Construction Co.Court of Appeals of Arizona · 1986
- Hawkins v. State, Dept. of Economic SEC.Court of Appeals of Arizona · 1995
- New Pueblo Const., Inc. v. LAKE PATAGONIA REC. ASSOCIATION, INC.Court of Appeals of Arizona · 1970
4 more not listed; retrieve them via the Exa API.
3Cited by29 opinions
- Comerica Bank v. MAHMOODICourt of Appeals of Arizona · 2010
- BMD CONTRACTORS v. Fidelity and Deposit Co. of Md.Court of Appeals for the Seventh Circuit · 2012
- Strojnik v. General Insurance Co. of AmericaCourt of Appeals of Arizona · 2001
- Western Corrections Group, Inc. v. TierneyCourt of Appeals of Arizona · 2004
- Wells Fargo Bank, N.A. v. AllenCourt of Appeals of Arizona · 2012