System Fuels, Inc. v. United States
United States Court of Federal Claims
1Opinion of the Court
OPINION AND ORDER
LETTOW, Judge.
The government has moved for reconsideration of the post-trial judgment entered October 16, 2007 in this contract case involving spent nuclear fuel (“SNF”). Judgment was entered on the basis of the court’s decision rendered on that same day. See System Fuels, Inc. v. United States, 79 Fed.Cl. 87, 2007 WL 3033659 (Oct. 16, 2007) (“System Fuels III”). The government’s motion raises two issues that merit discussion. One involves an issue of causation associated with the nature and extent of the Department of Energy’s contractual obligation to pick up SNF from…
2Cases cited17 opinions
- Caldwell, Iii v. United StatesCourt of Appeals for the Federal Circuit · 2004
- Indiana Michigan Power Company v. United StatesCourt of Appeals for the Federal Circuit · 2005
- Energy Capital Corp. (As General Partner of Energy Capital Partners Limited Partnership) v. United StatesCourt of Appeals for the Federal Circuit · 2002
- Fru-Con Construction Corp. v. United StatesUnited States Court of Federal Claims · 1999
- Citizens Federal Bank v. United StatesCourt of Appeals for the Federal Circuit · 2007
12 more not listed; retrieve them via the Exa API.
3Cited by15 opinions
- PCL Construction Services, Inc. v. United StatesUnited States Court of Federal Claims · 2008
- Boston Edison Co. v. United StatesUnited States Court of Federal Claims · 2012
- Petro-Hunt, L.L.C. v. United StatesUnited States Court of Federal Claims · 2012
- System Fuels, Inc. and Entergy Arkansas, Inc. v. United StatesUnited States Court of Federal Claims · 2015
- Alli v. United StatesUnited States Court of Federal Claims · 2009
10 more not listed; retrieve them via the Exa API.