This is a suit to enforce a lien on an oil and gas lease fQr material furnished in developing the lease. The evidence shows that before the development was begun the defendant John R. Hadley called pejisu pun jfuudnioo jfiddng jFM. po oto no it to furnish the material necessary to develop and operate the lease, and that the company agreed to do so. Under this arrangement the material was ordered from time to time as it was needed in the development of the lease.
The court submitted the case to the jury upon four interrogatories. Nos. 1 and 4 thereof are the only ones that need here be noted.…
2Cases cited3 opinions
- Atchison, T. & S. F. Ry. Co. v. BakerSupreme Court of Oklahoma · 1913
- Sherbondy v. Tulsa Boiler & MacHinery Co.Supreme Court of Oklahoma · 1924
- Joplin Sash & Door Works v. Oklahoma Presbyterian College for GirlsSupreme Court of Oklahoma · 1912
3Cited by6 opinions
- Rogers v. Crane Co.Supreme Court of Oklahoma · 1937
- Clark v. Oklahoma Electric Co.Supreme Court of Oklahoma · 1930
- Fox Rig Co. v. BellSupreme Court of Oklahoma · 1928
- Roxana Petroleum Corp. v. DormireSupreme Court of Oklahoma · 1933
- Gebhart v. United StatesOhio Supreme Court · 1961
1 more not listed; retrieve them via the Exa API.