Fuller v. Rosinski
Washington Supreme Court
1Opinion of the CourtRosellini, J.
In this action, the plaintiff sought to recover the unpaid balance on a contract to construct a rock wall and alpine area, and to prepare the ground and plant a lawn on the defendants’ residence property. The balance claimed due was $511.76. As an affirmative defense, the defendants alleged that the work had not been done properly and that it would cost as much or more than the balance due to remedy the defects.
The evidence showed that the work was done on a residential lot which had not been previously cultivated or graded, the house being situated in a new development. The plaintiff hauled…
2Cases cited5 opinions
- Dermott v. JonesSupreme Court of the United States · 1860
- White v. MitchellWashington Supreme Court · 1923
- Gilmartin v. Stevens Investment Co.Washington Supreme Court · 1953
- Baldwin v. AlbertiWashington Supreme Court · 1961
- Odgers v. HeldWashington Supreme Court · 1961
3Cited by12 opinions
- Eastlake Construction Co. v. HessWashington Supreme Court · 1984
- Alpine Industries, Inc. v. GohlCourt of Appeals of Washington · 1981
- Puget Sound Power & Light Co. v. ShulmanWashington Supreme Court · 1974
- Lancellotti v. ThomasSupreme Court of Pennsylvania · 1985
- Ducolon Mechanical, Inc. v. Shinstine/Forness, Inc.Court of Appeals of Washington · 1995