Baldwin v. Alberti
Washington Supreme Court
1Opinion of the CourtWeaver, J.
Defendant contracted to build a house for plaintiff on his land. The house was built and plaintiff paid defendant in full for its construction.
The contract provided, among other things:
“The contractor . . . shall remedy any defects due to faulty materials or workmanship which appear within a period of one year from the date of completion of the contract.” (Italics ours.)
Within a year, numerous defects appeared in the house. In the main, the defects were: (a) the grounds, which had been graded, did not drain properly and caused moisture to collect under the patio and house; (b) a portion of…
2Cases cited5 opinions
- Thorndike v. Hesperian Orchards, Inc.Washington Supreme Court · 1959
- State Ex Rel. MacRi v. City of BremertonWashington Supreme Court · 1941
- Spokane Truck & Dray Co. v. HoeferWashington Supreme Court · 1891
- Bernbaum v. HodgesWashington Supreme Court · 1953
- Odgers v. HeldWashington Supreme Court · 1961
3Cited by19 opinions
- Prier v. Refrigeration Engineering Co.Washington Supreme Court · 1968
- Eastlake Construction Co. v. HessWashington Supreme Court · 1984
- Buza v. Columbia Lumber CompanyAlaska Supreme Court · 1964
- Alpine Industries, Inc. v. GohlCourt of Appeals of Washington · 1981
- Carter v. QuickSupreme Court of Arkansas · 1978
14 more not listed; retrieve them via the Exa API.