Odgers v. Held
Washington Supreme Court
1Opinion of the CourtWeaver, J.
August 1, 1958, plaintiff, as builder, and defendants, as owners, entéred into a written contract for the construction of a residence on defendants’ property for:
“Total cost, plus a fixed fee of $1300.00. Total costs include labor, sub-contractors and materials; plus agreed 10(5 health and welfare and 8% of wages as overhead.”
Plaintiff built the house; defendants have paid him $25,450.
Plaintiff commenced this action to foreclose a lien for the unpaid balance, alleged to be $2,821. Defendants cross-complained for $17,500 damages for faulty construction.
The following findings of fact stand…
2Cases cited6 opinions
- White v. MitchellWashington Supreme Court · 1923
- Forrester v. CraddockWashington Supreme Court · 1957
- Baldwin v. AlbertiWashington Supreme Court · 1961
- Kenney v. AbrahamWashington Supreme Court · 1939
- Eckhardt v. HarderWashington Supreme Court · 1931
1 more not listed; retrieve them via the Exa API.
3Cited by7 opinions
- Prier v. Refrigeration Engineering Co.Washington Supreme Court · 1968
- Alpine Industries, Inc. v. GohlCourt of Appeals of Washington · 1981
- Baldwin v. AlbertiWashington Supreme Court · 1961
- Swenson v. LoweCourt of Appeals of Washington · 1971
- Fuller v. RosinskiWashington Supreme Court · 1971
2 more not listed; retrieve them via the Exa API.