Bailey Specialized Buildings, Inc. v. The United States
United States Court of Claims
1Opinion of the Court
SKELTON, Judge.
This is a contract case wherein the plaintiff seeks damages for a breach of contract or an equitable adjustment under the contract resulting from an alleged wrongful termination for default of the contract by the defendant. The defendant asserts a counterclaim growing out of excess costs suffered by it when required to pay an amount above plaintiff’s contract price to another contractor who supplied the products involved after plaintiff’s contract was terminated by the Government.
The facts involved in this case are substantially as follows:
The plaintiff was engaged in the…
2Cases cited11 opinions
- John Reiner & Company, Individually and to the Use of Kurz & Root Company (Incorporated) v. The United StatesUnited States Court of Claims · 1963
- Sol O. Schlesinger, Doing Business as Ideal Uniform Cap Company v. The United StatesUnited States Court of Claims · 1968
- Sundstrand Turbo, a Division of Sundstrand Corporation v. The United StatesUnited States Court of Claims · 1968
- Perini Corp. v. United StatesUnited States Court of Claims · 1967
- United States v. Burton Coal Co.Supreme Court of the United States · 1927
6 more not listed; retrieve them via the Exa API.
3Cited by31 opinions
- D. Joseph Devito, Receiver for Seaview Electric Company v. The United StatesUnited States Court of Claims · 1969
- J. D. Hedin Construction Company, Inc. v. The United StatesUnited States Court of Claims · 1969
- Urban Plumbing & Heating Co., an Oregon Corporation v. The United StatesUnited States Court of Claims · 1969
- General Builders Supply Co., Inc., on Behalf of Itself and for the Benefit of Hupp, Inc. v. The United StatesUnited States Court of Claims · 1969
- Mountain Home Contractors v. United StatesUnited States Court of Claims · 1970
26 more not listed; retrieve them via the Exa API.