Plaintiffs Carolina Power & Light Company (“CP & L”) and Florida Power Corporation (“FPC”) claim damages of $91,029,704 from Defendant caused by the failure of the Department of Energy (“DOE”) to collect and dispose of spent nuclear fuel beginning January 31, 1998 under the terms of DOE’s Standard Contract. CP & L and FPC are wholly-owned subsidiaries of Progress Energy, Inc., a public utility in the southeast United States. Plaintiffs’ damages consist of costs incurred in mitigation of DOE’s partial breach of the Standard Contract. This Court has jurisdiction…
2Cases cited38 opinions
- Bigelow v. RKO Radio Pictures, Inc.Supreme Court of the United States · 1946
- Eastman Kodak Co. v. Southern Photo Materials Co.Supreme Court of the United States · 1927
- Gould, Inc. v. The United StatesCourt of Appeals for the Federal Circuit · 1991
- Insurance Co. v. DutcherSupreme Court of the United States · 1877
- Indiana Michigan Power Company v. United StatesCourt of Appeals for the Federal Circuit · 2005
33 more not listed; retrieve them via the Exa API.
3Cited by27 opinions
- Carolina Power & Light Co. v. United StatesCourt of Appeals for the Federal Circuit · 2009
- Dairyland Power Cooperative v. United StatesUnited States Court of Federal Claims · 2009
- Wisconsin Electric Power Co. v. United StatesUnited States Court of Federal Claims · 2009
- Dominion Resources, Inc. v. United StatesUnited States Court of Federal Claims · 2008
- Entergy Nuclear Vermont Yankee, LLC v. United StatesUnited States Court of Federal Claims · 2010