Earl Dubey & Sons, Inc. v. MacOmb Concrete Corp.
Michigan Court of Appeals
1Opinion of the CourtD. E. Holbrook, J.
Plaintiff, Earl Dubey and Sons, Inc., commenced this action for rescission of an agreement as the result of the anticipatory breach by defendant, Macomb Concrete Corporation, and for damages in excess of $300,000. Plaintiff, Sentry Insurance, sought discharge of its liability on a performance bond. Defendant Macomb counter-claimed that plaintiffs were in default under the agreement and Macomb sought damages for fulfilling the contract by other means. Following a five-week trial, plaintiffs’ equitable claims were taken from the jury and resolved adversely to plaintiffs by the trial judge.…
2Cases cited9 opinions
- United States v. BehanSupreme Court of the United States · 1884
- Alderton v. WilliamsMichigan Supreme Court · 1905
- Palman v. ReynoldsMichigan Supreme Court · 1944
- Sexton v. American AggregatesMichigan Court of Appeals · 1975
- Jackson v. FoxMichigan Court of Appeals · 1976
4 more not listed; retrieve them via the Exa API.
3Cited by3 opinions
- Earl Dubey & Sons, Inc. v. MacOmb Contracting Corp.Michigan Court of Appeals · 1980
- Cleveland-Cliffs Iron Co. v. Chicago & North Western Transportation Co.District Court, W.D. Michigan · 1984
- Bertera Chrysler Plymouth, Inc. v. Chrysler Corp.District Court, D. Massachusetts · 1998