W. R. Pickering Lbr. Co. v. Fuller
Supreme Court of Oklahoma
1Opinion of the Court
Opinion by
STEPHENSON, C.
The W. R. Pickering Lumber Company commenced its action on a statutory builder’s bond for material sold and delivered to James G. Fuller et al. The Globe Indemnity Company, surety on the builder’s bond, was joined as a defendant. The builder’s bond was executed as provided by section 7486, C. O. S. 1921. in connection with a state highway project. James G. Fuller et al. were subcontractors, and purchased lumber from the plaintiff for use in connection with the construction of the state highway. The trial of the cause resulted in judgment for the defendants. The…
2Cases cited1 opinion
- Fuller v. BrooksSupreme Court of Oklahoma · 1926
3Cited by9 opinions
- Consolidated Cut Stone Co. v. SeidenbachSupreme Court of Oklahoma · 1937
- Tom P. McDermott, Inc. v. BennettSupreme Court of Oklahoma · 1964
- American Tank & Equipment Co. v. T. E. Wiggins, Inc.Supreme Court of Oklahoma · 1934
- Dorsett v. State Ex Rel. PriceSupreme Court of Oklahoma · 1930
- Tway v. ThompsonSupreme Court of Oklahoma · 1932
4 more not listed; retrieve them via the Exa API.