Ghilotti Construction Co. v. City of Richmond
California Court of Appeal
1Opinion of the Court
Opinion
PARRILLI, J.
In this case we hold that a public entity may waive inconsequential deviations from contract specifications in a public contract bid. To be considered inconsequential, a deviation must neither give the bidder an unfair competitive advantage nor otherwise defeat the goals of insuring economy and preventing corruption in the public contracting process.
Appellant Ghilotti Construction Company (GCC), the second lowest bidder on a contract for a road construction project in respondent City of Richmond (the City), petitioned the trial court for a writ of mandate or prohibition to…
2Cases cited18 opinions
- Miller v. McKinnonCalifornia Supreme Court · 1942
- Terminal Construction Corp. v. Atlantic County Sewerage AuthoritySupreme Court of New Jersey · 1975
- North Coast Business Park v. Nielsen Construction Co.California Court of Appeal · 1993
- Domar Electric, Inc. v. City of Los AngelesCalifornia Supreme Court · 1994
- City of Inglewood-Los Angeles County Civic Center Authority v. Superior CourtCalifornia Supreme Court · 1972
13 more not listed; retrieve them via the Exa API.
3Cited by24 opinions
- Kreeft v. City of OaklandCalifornia Court of Appeal · 1998
- People v. JTH Tax, Inc.California Court of Appeal · 2013
- MCM Constr., Inc. v. City & County of San FranciscoCalifornia Court of Appeal · 1998
- McBail & Co. v. Solano County Local Agency Formation CommissionCalifornia Court of Appeal · 1998
- Schram Construction, Inc. v. Regents of University of CaliforniaCalifornia Court of Appeal · 2010
19 more not listed; retrieve them via the Exa API.