Bates & Rogers Const. Co. v. Board of Com'rs
District Court, N.D. Ohio
At Raw. Action by the Bates & Rogers Construction Company against the Board of Commissioners of Cuyahoga County, Ohio. On demurrer to the petition.
1Opinion of the Court
WESTENHAVER, District Judge.
This cause is before me on general demurrer of defendant to the first cause of action in plaintiff’s petition. This cause of action is based on alleged breaches of a written contract for the construction of approaches to the Detroit-Superior bridge in the city of Cleveland, Ohio. The breaches complained of, and as a result of which plaintiff seeks to recover damages, are two: (1) That defendant failed in a reasonable time to deliver possession to the plaintiff of the sites upon which the approaches were to be constructed, as by its contract it was required to do.…
2Cases cited6 opinions
- Guerini Stone Co. v. P. J. Carlin Construction Co.Supreme Court of the United States · 1919
- Mansfield v. . N.Y.C. H.R.R.R. Co.New York Court of Appeals · 1886
- Blanchard v. Inhabitants of BlackstoneMassachusetts Supreme Judicial Court · 1869
- Larimore v. WellsOhio Supreme Court · 1875
- United States v. MuellerSupreme Court of the United States · 1885
1 more not listed; retrieve them via the Exa API.
3Cited by18 opinions
- J. A. Jones Construction Co. v. City of DoverSuperior Court of Delaware · 1977
- Hensler v. City of Los AngelesCalifornia Court of Appeal · 1954
- Gillioz v. State Highway CommissionSupreme Court of Missouri · 1941
- Thomas O'Connor & Co. v. City of MedfordMassachusetts Appeals Court · 1983
- Spitcaufsky v. State Highway CommissionSupreme Court of Missouri · 1941
13 more not listed; retrieve them via the Exa API.