In this action the plaintiff recovered $1,640.26. There was a motion for a new trial which was overruled, and the defendant appeals from the order overruling the motion, and from the judgment entered thereon. There is very little conflict in the evidence.
On the 31st day of August, 1927, the plaintiff and the defendant entered into a contract in writing, under which the plaintiff agreed to build a two story brick building in the city of Williston, N. D., furnishing' all the material, and all the work for the sum of $15,675. The first floor of the building was to be completed by…
2Cases cited9 opinions
- Schliess v. City of Grand RapidsMichigan Supreme Court · 1902
- Board of Commissioners v. O'ConnorIndiana Supreme Court · 1893
- Iron Clad Manufacturing Co. v. StanfieldCourt of Appeals of Maryland · 1910
- St. Anthony Falls Water Power Co. v. EastmanSupreme Court of Minnesota · 1874
- Siebert v. LeonardSupreme Court of Minnesota · 1871
4 more not listed; retrieve them via the Exa API.
3Cited by7 opinions
- Dobler v. MalloyNorth Dakota Supreme Court · 1973
- Dittmer v. NoklebergNorth Dakota Supreme Court · 1974
- Mannella v. PittsburghSupreme Court of Pennsylvania · 1939
- Carlson Homes, Inc. v. MessmerNorth Dakota Supreme Court · 1981
- Mayville-Portland School District No. 10 v. C. L. Linfoot Co.North Dakota Supreme Court · 1978
2 more not listed; retrieve them via the Exa API.