Hassett v. Dixie Furniture Co., Inc.
Supreme Court of North Carolina
1Opinion of the Court
WEBB, Justice.
The appellant’s first assignment of error deals with the jury instructions in regard to damages. The court instructed the jury that if it found the defendant had breached the 1 March 1986 contract, it could find that the plaintiff was entitled to recover as damages the total amount of the payments due to the plaintiff as if performance had been rendered under the contract.
There was evidence, some of it uncontradicted, that had the plaintiff performed he would have had a considerable amount of expense, including travel between his home in New Jersey and the defendant’s facilities…
2Cases cited16 opinions
- Calloway v. Ford Motor CompanySupreme Court of North Carolina · 1972
- Perfecting Service Co. v. Product Development & Sales Co.Supreme Court of North Carolina · 1963
- Troitino v. GoodmanSupreme Court of North Carolina · 1945
- News and Observer Publishing Co. v. PooleSupreme Court of North Carolina · 1992
- Tillis v. Calvine Cotton Mills, Inc.Supreme Court of North Carolina · 1959
11 more not listed; retrieve them via the Exa API.
3Cited by15 opinions
- Bartels Ex Rel. Bartels v. Saber Healthcare Group, LLCCourt of Appeals for the Fourth Circuit · 2018
- Robinson v. PowellSupreme Court of North Carolina · 1998
- City of Winston-Salem v. YarbroughCourt of Appeals of North Carolina · 1994
- North Carolina State Bar v. GilbertCourt of Appeals of North Carolina · 2008
- Potter v. Hilemn Laboratories, Inc.Court of Appeals of North Carolina · 2002
10 more not listed; retrieve them via the Exa API.