Elec-Trol, Inc. v. C. J. Kern Contractors, Inc.
Court of Appeals of North Carolina
1Opinion of the Court
MARTIN (Robert M.), Judge.
Plaintiff assigns as error the entry of summary judgment for the defendant and the third-party defendant. It argues that where the parties have not agreed that the architect’s decisions are final, the subcontractor may bring an action for payment of certain accepted change order work when changes were ordered by the contractor and the architect either failed to rule on the change order requests or ruled erroneously.
In support of this argument the plaintiff relies on three theories, the first of which is that the contract and subcontract do not provide that the…
2Cases cited4 opinions
- Vetco Concrete Company v. TROY LUMBER COMPANYSupreme Court of North Carolina · 1962
- Brokers, Inc. v. High Point City Board of EducationCourt of Appeals of North Carolina · 1977
- Welborn Plumbing & Heating Co. v. Randolph County Board of EducationSupreme Court of North Carolina · 1966
- J. R. Graham & Son, Inc. v. Randolph County Board of EducationCourt of Appeals of North Carolina · 1975
3Cited by10 opinions
- Rad-Razorback Ltd. Partnership v. B.G. Coney Co.Supreme Court of Arkansas · 1986
- Jennings Glass Co., Inc. v. BrummerCourt of Appeals of North Carolina · 1987
- Ruffin Woody & Associates, Inc. v. Person CountyCourt of Appeals of North Carolina · 1988
- Speedway Motorsports International Ltd. v. Bronwen Energy Trading, Ltd.Court of Appeals of North Carolina · 2011
- Propst Construction Co. v. North Carolina Department of TransportationCourt of Appeals of North Carolina · 1982