Canyon Contracting Co. v. Tohono O'Odham Housing Authority
Court of Appeals of Arizona
1Opinion of the Court
OPINION
CONTRERAS, Presiding Judge.
In this appeal, we consider whether the trial court erred in enforcing an alleged settlement agreement between the parties and in dismissing the action on that basis. We hold that Rule 80(d), Arizona Rules of Civil Procedure, applies to the alleged settlement agreement and that questions of fact precluded its enforcement.
The trial court held no evidentiary hearing in this case, but instead based its ruling entirely upon the arguments of counsel and documentary evidence in the record. In effect, the trial court granted summary judgment regarding the existence…
2Cases cited6 opinions
- Orme School v. ReevesArizona Supreme Court · 1990
- Hill-Shafer Partnership v. Chilson Family TrustArizona Supreme Court · 1990
- Miller v. Mason-McDuffie Co. of So. Cal.Arizona Supreme Court · 1987
- Hays v. FischerCourt of Appeals of Arizona · 1989
- Hackin v. RuppCourt of Appeals of Arizona · 1969
1 more not listed; retrieve them via the Exa API.
3Cited by12 opinions
- Ashfort Corp. v. Palmetto Construction Group, Inc.Supreme Court of South Carolina · 1995
- Robertson v. AllingArizona Supreme Court · 2015
- Althaus v. CornelioCourt of Appeals of Arizona · 2002
- Towne Development of Chandler, Inc. v. Superior CourtCourt of Appeals of Arizona · 1993
- Palmer v. PalmerCourt of Appeals of Arizona · 2007
7 more not listed; retrieve them via the Exa API.