Hercules Construction Co. v. C.J. Moritz Co.
Missouri Court of Appeals
1Opinion of the Court
DOWD, Judge.
Plaintiff-respondent Hercules Construction Company (hereinafter Hercules) brought suit for breach of contract against its subcontractor, C.J. Moritz Company (hereinafter Moritz) to recover expenses it incurred as general contractor in replacing a supply air fan at the St. Charles Civic Center. In the court tried case, defendant Moritz impleaded John F. Steffen Associates, Inc. (hereinafter Steffen), Western Engineering & Manufacturing Company (hereinafter Western), and Lyon Sheet Metal Works, Inc. (hereinafter Lyon), as third party defendants. At the close of Moritz’ evidence, the…
2Cases cited8 opinions
- Murphy v. CarronSupreme Court of Missouri · 1976
- Smith v. Old Warson Development CompanySupreme Court of Missouri · 1972
- Berghorn v. Reorganized School District No. 8Supreme Court of Missouri · 1953
- North County School District R-1 v. Fidelity & Deposit Co. of MarylandMissouri Court of Appeals · 1976
- Gundaker v. TemplerMissouri Court of Appeals · 1977
3 more not listed; retrieve them via the Exa API.
3Cited by6 opinions
- Schaefer v. RiversMissouri Court of Appeals · 1998
- Gilmartin Bros., Inc. v. KernMissouri Court of Appeals · 1995
- Wyrozynski v. NicholsMissouri Court of Appeals · 1988
- Means v. ClardyMissouri Court of Appeals · 1987
- Missouri Farmers Ass'n v. CampbellMissouri Court of Appeals · 1988
1 more not listed; retrieve them via the Exa API.