Kasler/Continental Heller/Fruin Colnon v. United States
United States Court of Claims
1Opinion of the Court
OPINION
NETTESHEIM, Judge.
Defendant has moved, over plaintiff’s opposition, for partial summary judgment dismissing Count I of plaintiff’s complaint.
FACTS
The following facts are not disputed. This case concerns a contract between Kasler/Continental Heller/Fruin Colnon (“plaintiff”) and the Army Corps of Engineers (the “Corps”) for the construction of the Space Transportation System-Package II at Launch Complex Six, Vandenberg Air Force Base, California. On February 15, 1983, plaintiff, pursuant to the Contract Disputes Act, 41 U.S.C. §§ 601-613 (1982) (the “CDA”), submitted to contracting…
2Cases cited7 opinions
- Nager Electric Company, Inc. And Keystone Engineering Corporation v. The United StatesUnited States Court of Claims · 1966
- Z.A.N. Co. v. United StatesUnited States Court of Claims · 1984
- Gregory Lumber Co. v. United StatesUnited States Court of Claims · 1982
- United Construction Co. v. United StatesUnited States Court of Claims · 1984
- Cosmopolitan Manufacturing Co. v. United StatesUnited States Court of Claims · 1962
2 more not listed; retrieve them via the Exa API.
3Cited by11 opinions
- Pathman Construction Company, Inc. v. The United StatesCourt of Appeals for the Federal Circuit · 1987
- LaCoste v. United StatesUnited States Court of Claims · 1986
- Spalding & Son, Inc. v. United StatesUnited States Court of Claims · 1991
- Turner Construction Co. v. United StatesUnited States Court of Claims · 1985
- Borough of Alpine v. United StatesUnited States Court of Claims · 1990