United Surety & Indemnity Co. v. United States
United States Court of Federal Claims
1Opinion of the Court
MEMORANDUM OPINION AND FINAL ORDER
BRADEN, Judge.
I. RELEVANT FACTUAL BACKGROUND.1
On February 6, 2001, the United States Postal Service (“USPS”) awarded Selpa Construction & Rental Equipment Corporation (“Selpa”) a contract, # 332495-00-B-0221 (“the Contract”), to construct a post office in Fajardo, Puerto Rico. See Compl. ¶ 4. The initial amount of the Contract was $2,288,000.00, but the amount was later increased to $2,568,648.60 through change orders. Id. Clause B-8, found in the USPS Procurement Manual and incorporated into the Contract, prohibited assignment of the Contract to any party…
2Cases cited25 opinions
- Ashcroft v. IqbalSupreme Court of the United States · 2009
- Bell Atlantic Corp. v. TwomblySupreme Court of the United States · 2007
- Lujan v. Defenders of WildlifeSupreme Court of the United States · 1992
- Warth v. SeldinSupreme Court of the United States · 1975
- Friends of the Earth, Inc. v. Laidlaw Environmental Services (TOC), Inc.Supreme Court of the United States · 2000
20 more not listed; retrieve them via the Exa API.
3Cited by5 opinions
- Brittani Nicole Williams v. United StatesUnited States Court of Federal Claims · 2013
- Hartford Fire Insurance v. United StatesUnited States Court of Federal Claims · 2012
- M.E.S., Inc. v. United StatesUnited States Court of Federal Claims · 2012
- Colonial Surety Co. v. United StatesUnited States Court of Federal Claims · 2013
- United Surety & Indemnity Co. v. United StatesUnited States Court of Federal Claims · 2009