Court of Appeals for the Eighth Circuit

Decided July 10, 2014No. 13-1918PublishedCited by 5 opinions

1Opinion of the Court

SMITH, Circuit Judge.

enXco Development Corp. (“enXco”) and Northern States Power Co. (NSP) contracted for the construction of a wind-energy project in North Dakota. enXco did not obtain a permit by a date certain, thus failing to satisfy a condition precedent to the contract. NSP then terminated the contract. enXco suffered several million dollars in losses.

enXco sued NSP for breach of contract. The district court1 granted NSP’s motion for summary judgment. On appeal, enXco contends that the district court erred in granting NSP’s motion for summary judgment because the doctrines of temporary…

2Cases cited12 opinions

  1. Metropolitan Sports Facilities Commission v. General Mills, Inc.Supreme Court of Minnesota · 1991
  2. Klipsch, Inc. v. Wwr Technology, Inc.Court of Appeals for the Eighth Circuit · 1997
  3. St. Paul Dredging Co. v. StateSupreme Court of Minnesota · 1961
  4. Harleysville Insurance Company v. Physical Distribution ServicesCourt of Appeals for the Eighth Circuit · 2013
  5. Village of Minneota v. Fairbanks, Morse & Co.Supreme Court of Minnesota · 1948

7 more not listed; retrieve them via the Exa API.

3Cited by5 opinions

  1. Capistrant v. Lifetouch National School Studios, Inc.Court of Appeals of Minnesota · 2017
  2. Schnuck Markets, Inc. v. First Data Merchant Data Services Corp.District Court, E.D. Missouri · 2015
  3. Hampton v. KohlerDistrict Court, D. Minnesota · 2019
  4. Hillcrest Center, LLC v. Ton Real Estate Investments III, LLCDistrict Court, D. Minnesota · 2021
  5. Jacobson Warehouse Co., Inc. v. Schnuck Markets, Inc.District Court, E.D. Missouri · 2020

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API