Clemmer Const. Co. v. United States
United States Court of Claims
1Opinion of the Court
MADDEN, Judge.
The Government has demurred to the plaintiff’s petition. According to the petition, the plaintiff, after competitive bidding, was awarded a contract for the erection of a war housing project at Akron, Ohio. The project was to contain 90 buildings, with 500 apartment units. The contract was dated February 6, 1943, and the plaintiff’s compensation was to be two fixed sums, one for labor and one for materials. The Government’s invitation for bids, and the contract, when signed, specified the wage rates to be paid on the contract, and the contract required that time and one-half be…
2Cases cited6 opinions
- Horowitz v. United StatesSupreme Court of the United States · 1925
- Jones v. United StatesUnited States Court of Claims · 1865
- Deming v. United StatesUnited States Court of Claims · 1865
- Standard Accident Ins. Co. v. United StatesUnited States Court of Claims · 1945
- Hallman v. United StatesUnited States Court of Claims · 1946
1 more not listed; retrieve them via the Exa API.
3Cited by16 opinions
- Sunswick Corporation v. United StatesUnited States Court of Claims · 1948
- Piggly Wiggly Corporation v. United StatesUnited States Court of Claims · 1949
- Ottinger v. United StatesUnited States Court of Claims · 1950
- Walter Dawgie Ski Corp. v. United StatesUnited States Court of Federal Claims · 1993
- J. B. McCrary Co. v. United StatesUnited States Court of Claims · 1949
11 more not listed; retrieve them via the Exa API.