J. B. McCrary Co. v. United States
United States Court of Claims
1Opinion of the Court
WHITAKER, Judge.
On January 26, 1943, plaintiff entered into a contract with defendant for the construction of 65 buildings at a place called Warner-Robins, Georgia, which was about 15 miles from Macon, Georgia. The contract required plaintiff to pay its brick-masons $1.25 an hour, its carpenters $1.00 an hour, and common labor 40 cents an hour. Plaintiff was unable to get sufficient labor at these wages and as a result thereof was delayed in the performance of its contract for 186 days. Defendant was also late in furnishing roughing-in drawings for the plumbing, and in failing to deliver…
2Cases cited6 opinions
- Horowitz v. United StatesSupreme Court of the United States · 1925
- Sunswick Corporation v. United StatesUnited States Court of Claims · 1948
- Clemmer Const. Co. v. United StatesUnited States Court of Claims · 1947
- Froemming Bros., Inc., of Texas v. United StatesUnited States Court of Claims · 1947
- J. F. Barbour & Sons v. United StatesUnited States Court of Claims · 1944
1 more not listed; retrieve them via the Exa API.
3Cited by12 opinions
- Anthony P. Miller, Inc. v. United StatesUnited States Court of Claims · 1963
- Winstar Corp. v. United StatesUnited States Court of Claims · 1992
- Amino Brothers Company, Inc. v. The United StatesUnited States Court of Claims · 1967
- Tony Downs Foods Co. v. United StatesUnited States Court of Claims · 1976
- Wah Chang Corporation v. United StatesUnited States Court of Claims · 1960