Andrews Distributing Co. v. Oak Square at Gatlinburg, Inc.
Tennessee Supreme Court
1Opinion of the Court
OPINION
FONES, Justice.
This is an action by a materialman for enforcement of a materialman’s lien, or in the alternative for recovery under the general contractor’s labor and material payment bond. The trial court dismissed the action for failure to give timely written notice of lien and for failure to give timely notice under the terms of the bond. The Court of Appeals affirmed, and this Court granted plaintiff’s application for permission to appeal.
In October, 1984, plaintiff, Andrews Distributing Company, received a purchase order for HVAC [heating and air conditioning] units from Mike…
2Cases cited9 opinions
- Armour & Co. v. TomlinTexas Commission of Appeals · 1933
- Hartford Accident & Indemnity Co. v. CreasyTennessee Supreme Court · 1975
- New Memphis Gaslight Co.Tennessee Supreme Court · 1900
- General Electric Supply Co. v. Arlen Realty & Development Corp.Tennessee Supreme Court · 1977
- Thompson v. BaxterTennessee Supreme Court · 1893
4 more not listed; retrieve them via the Exa API.
3Cited by5 opinions
- Spence v. Allstate Insurance Co.Tennessee Supreme Court · 1994
- Vulcan Materials Co. v. Gamble Construction Co.Court of Appeals of Tennessee · 2001
- Andrews Distributing Co. v. Oak Square at Gatlinburg, Inc.Tennessee Supreme Court · 1988
- Ronnie Bradfield v. City of MemphisCourt of Appeals of Tennessee · 1999
- Ruffin Buildling Systems, Inc. v. Larry Gene Varner, an individualCourt of Appeals of Tennessee · 2004