Turner Construction Co., Inc. v. United States
United States Court of Federal Claims
1Opinion of the Court
OPINION AND ORDER
FUTEY, Judge.
This is a post-award bid protest related to a contract for the replacement of Fort Ben-ning’s Martin Army Community Hospital (“the Hospital”). The United States Army *563Corps of Engineers (“the Army”) awarded that contract to Turner Construction Company (“Turner”) on September 28, 2009. Turner’s two rivals for the contract, McCarthy/Hunt, JV (“MeCarthy/Hunt”), and B.L. Harbert-Brasfield & Gome, JV (“Har-bert/Gorrie”), who now intervene in this case, filed bid protests with the Government Accountability Office (“GAO”) in November 2009. The GAO on February 16, 2010…
2Cases cited28 opinions
- Motor Vehicle Mfrs. Assn. of United States, Inc. v. State Farm Mut. Automobile Ins. Co.Supreme Court of the United States · 1983
- Federal Communications Commission v. Fox Television Stations, Inc.Supreme Court of the United States · 2009
- Baltimore Gas & Electric Co. v. Natural Resources Defense Council, Inc.Supreme Court of the United States · 1983
- Bannum, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2005
- Impresa Construzioni Geom. Domenico Garufi v. United StatesCourt of Appeals for the Federal Circuit · 2001
23 more not listed; retrieve them via the Exa API.
3Cited by37 opinions
- Turner Const. Co., Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2011
- Systems Application & Technologies, Inc. v. United StatesUnited States Court of Federal Claims · 2011
- Furniture By Thurston v. United StatesUnited States Court of Federal Claims · 2012
- L-3 Communications Corp. v. United StatesUnited States Court of Federal Claims · 2011
- Jacobs Technology Inc. v. United StatesUnited States Court of Federal Claims · 2011
32 more not listed; retrieve them via the Exa API.