Turner Const. Co., Inc. v. United States
Court of Appeals for the Federal Circuit
1Opinion of the Court
PROST, Circuit Judge.
The United States Army Corps of Engineers (“Army”) awarded Appellee Turner Construction Company, Inc. (“Turner”) a contract for the construction of a government hospital. Turner’s two rival bidders for the contract, Appellant B.L. Harbert-Brasfield & Gorrie (“Harbert-Gorrie”) and McCarthy/Hunt, each filed a bid protest with the Government Accountability Office (“GAO”). The GAO recommended that the contract be re-procured without Turner’s participation. In due course, the Army announced that it would follow the GAO’s recommendation and terminated Turner’s contract. Turner…
2Cases cited11 opinions
- Axiom Resource Management, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2009
- Pgba, LLC v. United States, and Wisconsin Physicians Service Insurance CorporationCourt of Appeals for the Federal Circuit · 2004
- Honeywell, Inc. v. The United States v. Haz-Tad, Inc.Court of Appeals for the Federal Circuit · 1989
- Centech Group, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2009
- Caci, Inc.-Federal v. The United StatesCourt of Appeals for the Federal Circuit · 1983
6 more not listed; retrieve them via the Exa API.
3Cited by147 opinions
- Systems Application & Technologies, Inc. v. United StatesCourt of Appeals for the Federal Circuit · 2012
- Glenn Defense Marine (Asia), PTE Ltd. v. United StatesCourt of Appeals for the Federal Circuit · 2013
- Dell Federal Systems, L.P. v. United StatesCourt of Appeals for the Federal Circuit · 2018
- Cw Government Travel, Inc., D/B/A Cwtsatotravel v. United StatesUnited States Court of Federal Claims · 2013
- Sierra Nevada Corp. v. United StatesUnited States Court of Federal Claims · 2012
142 more not listed; retrieve them via the Exa API.