United States Fidelity & Guaranty Co. v. E. I. Dupont De Nemours & Co.
Washington Supreme Court
1Opinion of the CourtHolcomb, J.
After the completion of a contract for highway construction, a number of claims were filed against appellant, as surety on the contractors’ bond, and with the director of highways against the retained percentage withheld by the department of highways. This action was instituted to ascertain the validity of these claims, to determine the amount of retained percentage upon the contract, and to have such amount paid into the registry of the court for disbursement in liquidation of the valid claims.
Ed. Bjork and William Strom, individually and as joint administrators of the copartnership estate…
2Cases cited14 opinions
- National Surety Co. v. Bratnober Lumber Co.Washington Supreme Court · 1912
- National Surety Co. v. United States ex rel. Pittsburgh & Buffalo Co.Court of Appeals for the Sixth Circuit · 1916
- United States Rubber Co. of California v. American Bonding Co. of BaltimoreWashington Supreme Court · 1915
- Sturtevant Co. v. Fidelity & Deposit Co.Washington Supreme Court · 1916
- Brace & Hergert Mill Co. v. BurbankWashington Supreme Court · 1915
9 more not listed; retrieve them via the Exa API.
3Cited by20 opinions
- Standard Lumber Co. v. FieldsWashington Supreme Court · 1947
- Willett v. DavisWashington Supreme Court · 1948
- Sandel & Lastrapes v. City of ShreveportLouisiana Court of Appeal · 1961
- Warren v. Washington Trust BankWashington Supreme Court · 1979
- Holtz v. BabcockMontana Supreme Court · 1963
15 more not listed; retrieve them via the Exa API.