Legal Opinion

Metropolitan Paving Co. v. United States

United States Court of Claims

Decided December 13, 1963No. 509-58PublishedCited by 10 opinions

1Opinion of the CourtDurfee, Judge

This is an action for delay damages growing out of defendant’s alleged breach of contract. The contract in question was entered into November 18, 1954. Under the contract, plaintiff undertook to complete additional airfield paving and other work at the Walker Air Force Base, Eos-well, New Mexico. The total consideration was $2,072,739.61.

Under the contract, plaintiff was to commence work within ten days of receipt of the contract; to complete the work not later than 300 calendar days from the commencement date; and to “complete work within landing areas” as expeditiously as practicable. The…

2Cases cited4 opinions

  1. United States v. Blair Ex Rel. Roanoke Marble & Granite Co.Supreme Court of the United States · 1944
  2. George A. Fuller Co. v. United StatesUnited States Court of Claims · 1947
  3. Rogers v. United StatesUnited States Court of Claims · 1943
  4. Great Lakes Construction Co. v. United StatesUnited States Court of Claims · 1942

3Cited by10 opinions

  1. Broome Construction, Inc. v. United StatesUnited States Court of Claims · 1974
  2. Gardner Displays Company v. The United StatesUnited States Court of Claims · 1965
  3. Weaver-Bailey Contractors, Inc. v. United StatesUnited States Court of Claims · 1990
  4. Gardner Displays Co. v. United StatesUnited States Court of Claims · 1965
  5. Sun Shipbuilding & Dry Dock Co. v. United States Lines, Inc.District Court, E.D. Pennsylvania · 1977

5 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API