Pacific Gas & Electric Co. v. United States
United States Court of Federal Claims
1Opinion of the Court
OPINION 1
HEWITT, Chief Judge.
I. Introduction
This case is before the court on remand for the purpose of redetermining damages in accordance with the opinion of the United States Court of Appeals for the Federal Circuit (Federal Circuit), Pacific Gas & Electric Co. v. United States (PG & E II), 536 F.3d 1282 (Fed.Cir.2008), affirming-in-part, reversing-in-part and remanding Pacific Gas & Electric Co. v. United States (PG & E I), 73 Fed.Cl. 333 (2006). The Federal Circuit’s opinion in PG & E II concluded that “the Standard Contract required [the Department of Energy (DOE) ] to accept [spent…
2Cases cited26 opinions
- John R. Sand & Gravel Co. v. United StatesSupreme Court of the United States · 2008
- In Re Sanford Fork & Tool Co.Supreme Court of the United States · 1895
- John R. Sand & Gravel Co. v. United StatesSupreme Court of the United States · 2008
- Franconia Associates v. United StatesSupreme Court of the United States · 2002
- Indiana Michigan Power Company v. United StatesCourt of Appeals for the Federal Circuit · 2005
21 more not listed; retrieve them via the Exa API.
3Cited by11 opinions
- Pacific Gas & Electric Co. v. United StatesCourt of Appeals for the Federal Circuit · 2012
- Boston Edison Co. v. United StatesUnited States Court of Federal Claims · 2010
- Yankee Atomic Power Co. v. United StatesUnited States Court of Federal Claims · 2010
- Kansas Gas & Electric Co. v. United StatesUnited States Court of Federal Claims · 2010
- Carolina Power & Light Co. v. United StatesUnited States Court of Federal Claims · 2011
6 more not listed; retrieve them via the Exa API.