Application of Northern States Power Co.
South Dakota Supreme Court
1Opinion of the Court
HENDERSON, Justice.
ACTION
Northern States Power Company (NSP) applied to the South Dakota Public Utilities Commission (PUC) for an increase in electric rates to cover NSP’s projected losses related to the Tyrone nuclear power project. The PUC decided to defer ruling on NSP’s application until the Federal Energy Regulatory Commission (FERC) decided what NSP’s losses were.
NSP appealed to the circuit court, wherein the PUC’s decision was reversed as being beyond the PUC’s statutory authority. This appeal ensued.
On the federal level, FERC has approved the losses claimed by NSP; however, the PUC…
2Cases cited15 opinions
- Baker v. CarrSupreme Court of the United States · 1962
- Permian Basin Area Rate CasesSupreme Court of the United States · 1968
- Application of Dakota Transp. Co.South Dakota Supreme Court · 1940
- Valley State Bank of Canton v. Farmers State BankSouth Dakota Supreme Court · 1973
- In Re the South Lincoln Rural Water System Application for Permit No. 4300-3South Dakota Supreme Court · 1980
10 more not listed; retrieve them via the Exa API.
3Cited by14 opinions
- Matter of SD Water Mgmt. Bd.South Dakota Supreme Court · 1984
- Tri County Landfill Ass'n v. Brule CountySouth Dakota Supreme Court · 1995
- Keogan v. BerghSouth Dakota Supreme Court · 1984
- State Ex Rel. Johnson v. Public Utilities CommissionSouth Dakota Supreme Court · 1986
- In re Declaratory Ruling re SDCL 62-1-1(6)South Dakota Supreme Court · 2016