Severin v. United States
United States Court of Claims
1Opinion of the CourtMadden, Judge
Plaintiffs entered into a contract with the United States on August 3, 1933, to furnish all labor and materials and perform all work required for “the construction, including approaches, etc., of the Post Office at Eochester, New York, per Bid No. 4 (using sandstone for all exterior stonework *441except where marble and granite are required and substituting steel casement windows for the aluminum casement windows)” for a consideration of $805,923.00, in accordance with designated drawings and specifications. The work was to be completed within 540 days after receipt of the notice to proceed.…
2Cases cited6 opinions
- Spofford v. KirkSupreme Court of the United States · 1878
- Nortz v. United StatesSupreme Court of the United States · 1935
- National Bank of Commerce v. DownieSupreme Court of the United States · 1910
- H. Herfurth, Jr., Inc. v. United StatesUnited States Court of Claims · 1939
- Great Lakes Construction Co. v. United StatesUnited States Court of Claims · 1942
1 more not listed; retrieve them via the Exa API.
3Cited by138 opinions
- The United States v. Johnson Controls, Inc.Court of Appeals for the Federal Circuit · 1983
- G. L. Christian and Associates v. The United StatesUnited States Court of Claims · 1963
- Blount Brothers Construction Company v. The United StatesUnited States Court of Claims · 1965
- J. L. Simmons Company, Inc. v. The United StatesUnited States Court of Claims · 1969
- Clark-Fitzpatrick, Inc./Franki Foundation Co. v. GillSupreme Court of Rhode Island · 1994
133 more not listed; retrieve them via the Exa API.