George Leary Construction Co. v. United States
United States Court of Claims
Decided February 23, 1927No. D-39PublishedCited by 9 opinions
1Opinion of the CourtBooth, Judge
The contract furnishing the basis of this suit provided in part as follows:
“ Adjustment of wages. — If, after the date of the contract, there shall be any increase in the rates of wages prevailing in the vicinity of a place where work contemplated by the contract is done that shall necessitate payment by the contractor on account of labor employed exclusively upon such work of rates of wages in excess of those prevailing in such vicinity at the date of the contract, he shall receive additional compensation in a sum equal to one-half the amount of the increase in the rates of wages so required…
2Cases cited5 opinions
- United States v. BehanSupreme Court of the United States · 1884
- Merritt v. United StatesSupreme Court of the United States · 1925
- Anvil Mining Co. v. HumbleSupreme Court of the United States · 1894
- United States v. AxmanSupreme Court of the United States · 1914
- Yale & Towne Manufacturing Co. v. United StatesUnited States Court of Claims · 1923
3Cited by9 opinions
- Seaboard Lumber Company and Capital Development Company v. United StatesCourt of Appeals for the Federal Circuit · 2002
- Morrison Knudsen Corp. v. Fireman's Fund InsuranceCourt of Appeals for the Tenth Circuit · 1999
- Roof-Techs International, Inc. v. StateCourt of Appeals of Kansas · 2002
- Armour of America v. United StatesUnited States Court of Federal Claims · 2011
- Schwartz v. United StatesUnited States Court of Claims · 1946
4 more not listed; retrieve them via the Exa API.