Legal Opinion

Estes Express Lines v. United States

United States Court of Federal Claims

Decided January 15, 2013No. 11-597CPublishedCited by 3 opinions

1Opinion of the Court

Contract case; Motion to dismiss under RCFC 12(b)(1) and 12(b)(6); Standard of review; Subcontractor lacked privity of contract with the United States; Contractor was not agent of Federal agency; 49 U.S.C. § 13706; Case dismissed for lack of jurisdiction.

OPINION

ALLEGRA, Judge.

This contract case is before the court on defendant’s motion to dismiss the complaint pursuant to RCFC 12(b)(1) or, alternatively, RCFC 12(b)(6). The plaintiff, Estes Express Lines, Inc. (Estes Express or plaintiff), an interstate motor carrier, claims that an arm of the United States Department of Defense breached…

2Cases cited27 opinions

  1. Bell Atlantic Corp. v. TwomblySupreme Court of the United States · 2007
  2. Karen S. Reynolds v. Army and Air Force Exchange ServiceCourt of Appeals for the Federal Circuit · 1988
  3. Rmi Titanium Company v. Westinghouse Electric CorporationCourt of Appeals for the Sixth Circuit · 1996
  4. John G. Rocovich, Jr. v. The United StatesCourt of Appeals for the Federal Circuit · 1991
  5. John D. Holley v. United StatesCourt of Appeals for the Federal Circuit · 1997

22 more not listed; retrieve them via the Exa API.

3Cited by3 opinions

  1. Estes Express Lines v. United StatesCourt of Appeals for the Federal Circuit · 2014
  2. Rudolph and Sletten, Inc. v. United StatesUnited States Court of Federal Claims · 2015