Delmarva Power & Light Company v. Federal Energy Regulatory Commission, Cities of Newark and New Castle, Delaware, Intervenors
Court of Appeals for the D.C. Circuit
1Opinion of the Court
BORK, Circuit Judge:
Delmarva Power & Light Company petitions for review of a decision of the Federal Energy Regulatory Commission refusing to include the annualized costs of a new generating plant in Delmarva’s test period rate base. Our jurisdiction is based on 16 U.S.C. § 825Z (b) (1982).
Delmarva had the burden of establishing that the annualization method it chose resulted in a test-year estimate reasonable when made. The Commission’s Administrative Law Judge (“ALJ”) held that Delmarva had not carried its burden, and the Commission summarily affirmed that aspect of the ALJ’s decision. For…
2Cases cited12 opinions
- Securities & Exchange Commission v. Chenery Corp.Supreme Court of the United States · 1943
- Federal Power Commission v. Colorado Interstate Gas Co.Supreme Court of the United States · 1955
- Papago Tribal Utility Authority v. Federal Energy Regulatory Commission, Arizona Public Service Company and Arizona Power Authority, IntervenorsCourt of Appeals for the D.C. Circuit · 1980
- Municipal Light Boards of Reading and Wakefield Massachusetts v. Federal Power Commission, Boston Edison Company, IntervenorCourt of Appeals for the D.C. Circuit · 1971
- Edwin I. Hatch v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 1981
7 more not listed; retrieve them via the Exa API.
3Cited by8 opinions
- City of Vernon, California v. Federal Energy Regulatory Commission, Southern California Edison Company, Cities of Anaheim, Riverside, IntervenorsCourt of Appeals for the D.C. Circuit · 1988
- National Black Media Coalition v. Federal Communications Commission, Walt-West Enterprises, Inc., IntervenorCourt of Appeals for the D.C. Circuit · 1985
- Southwestern Public Service Co. v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 1992
- City of Vernon, California v. Federal Energy Regulatory Commission, Southern California Edison Company, Cities of Anaheim, Riverside, IntervenorsCourt of Appeals for the D.C. Circuit · 1988
- Delmarva Power & Light Co. v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 1989
3 more not listed; retrieve them via the Exa API.