Legal Opinion

Danos & Curole Marine Contractors, Inc. v. BP America Production Co.

District Court, S.D. Texas

Decided November 19, 2014No. Civil Action No. H-13-3803PublishedCited by 1 opinion

1Opinion of the Court

Amended Memorandum Opinion & Order 1

GRAY H. MILLER, District Judge.

Pending before the court is plaintiff Da-nos & Curóle Contractors LLC’s (“Da-nos”) motion for partial summary judgment (Dkt. 20), and defendant BP America Production Company’s (“BP”) cross motion for summary judgment (Dkt. 22). Upon consideration of the motion, responses, and applicable law, Danos’ motion (Dkt. 20) is GRANTED and BP’s motion (Dkt. 22) is DENIED.

I. Background

Danos provides operations and maintenance labor services for BP on a platform in the Gulf of Mexico called “Marlin.” Dkt. 20-1 at 2-3. The platform is…

2Cases cited11 opinions

  1. Celotex Corp. v. Catrett, Administratrix of the Estate of CatrettSupreme Court of the United States · 1986
  2. Little v. Liquid Air Corp.Court of Appeals for the Fifth Circuit · 1994
  3. TIG Insurance v. Sedgwick James of WashingtonCourt of Appeals for the Fifth Circuit · 2002
  4. Moore v. Willis Independent School DistrictCourt of Appeals for the Fifth Circuit · 2000
  5. Environmental Conservation Organization v. City of DallasCourt of Appeals for the Fifth Circuit · 2008

6 more not listed; retrieve them via the Exa API.

3Cited by1 opinion

  1. Total E&P USA, Inc. v. Marubeni Oil & Gas (Usa), Inc.District Court, S.D. Texas · 2018