In re Application of Columbus S. Power Co.
Ohio Supreme Court
1Opinion of the Court
[Cite as In re Application of Columbus S. Power Co., 138 Ohio St.3d 448,
2014-Ohio-462.] IN RE APPLICATION OF COLUMBUS SOUTHERN POWER COMPANY ET AL.; INDUSTRIAL ENERGY USERS-OHIO ET AL., APPELLANTS; PUBLIC UTILITIES COMMISSION, APPELLEE; OHIO POWER COMPANY, INTERVENING APPELLEE. [Cite as In re Application of Columbus S. Power Co., 138 Ohio St.3d 448,
2014-Ohio-462.] Public utilities—Electric security plan—R.C. 4928.143—Commission’s decision to permit recovery of carrying charges under R.C. 4928.143(B)(2)(d) was lawful and reasonable—Utility not required to prove charges are “necessary” in order…
2Cases cited20 opinions
- Office of Consumers' Counsel v. Public Utilities CommissionOhio Supreme Court · 1979
- Columbia Gas Transmission Corp. v. LevinOhio Supreme Court · 2008
- Constellation NewEnergy, Inc. v. Public Utilities CommissionOhio Supreme Court · 2004
- Monongahela Power Co. v. Public Utilities CommissionOhio Supreme Court · 2004
- Ohio Edison Co. v. Public Utilities CommissionOhio Supreme Court · 1997
15 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- In re Application of Buckeye Wind, L.L.C. (Slip Opinion)Ohio Supreme Court · 2016