Bishop Engineering Co. v. United States
United States Court of Claims
1Opinion of the CourtDureee, Judge
This is an action for breach of a fixed price research and development contract for the design, manufacture and furnishing of an instrumentation semi-trailer vehicle by plaintiff, a Maryland Corporation for defendant, acting through the National Aeronautics and Space Administration (NASA) at a price, as subsequently amended, of $79,093.47.
Specifications of the contract called for a trailer approximately 39 feet long. Plaintiff alleges that it designed such a trailer but that defendant indicated it required a longer trailer and by constructive change compelled plaintiff to redesign and build a…
2Cases cited15 opinions
- Hol-Gar Manufacturing Corp. v. The United StatesUnited States Court of Claims · 1965
- WPC Enterprises, Inc. v. United StatesUnited States Court of Claims · 1963
- Blount Brothers Construction Company v. The United StatesUnited States Court of Claims · 1965
- Southern Construction Company, Inc. v. The United StatesUnited States Court of Claims · 1966
- The Jack Stone Company, Inc. v. The United StatesUnited States Court of Claims · 1965
10 more not listed; retrieve them via the Exa API.
3Cited by32 opinions
- Mason v. United StatesUnited States Court of Claims · 1980
- Astro-Space Laboratories, Inc. v. United StatesUnited States Court of Claims · 1972
- Perry and Wallis, Inc. v. The United StatesUnited States Court of Claims · 1970
- John C. Grimberg Co. v. United StatesUnited States Court of Claims · 1985
- PCL Construction Services, Inc. v. United StatesUnited States Court of Federal Claims · 2000
27 more not listed; retrieve them via the Exa API.