PROM SHELBY. Appeal from Chancery Court. of Shelby County.— F. H. Heiskell, Chancellor.
1Opinion of the CourtJustice Neil
The bill in this ease was filed in the chancery court at Memphis on September 11, 1901, to recover for breach of contract to deliver to the complainant 5,000 bundles of cotton arrow ties, during August, 1901, at $1 per bundle.
The defendants do not deny making the contract, but claim that it ivas canceled by agreement of the parties.
The facts bearing upon this subject, so far as necessary to be stated, are as follows: The contract was made, as stated, on June 13, 1901, for the delivery of the 5,000 bundles of ties at the price stated, at any time during the month of August of the same year, at…
2Cases cited4 opinions
- Ault v. DustinTennessee Supreme Court · 1898
- Paragon Refining Co. v. Lee Bros.Tennessee Supreme Court · 1897
- Cole v. ZucarelloTennessee Supreme Court · 1900
- Coffman v. WilliamsTennessee Supreme Court · 1871
3Cited by6 opinions
- Akers v. J. B. Sedberry, Inc.Court of Appeals of Tennessee · 1955
- Inman v. Elk Cotton MillsTennessee Supreme Court · 1905
- Coppock v. RobertsOregon Supreme Court · 1925
- Lagerloef Trading Co. v. American Paper Products Co.Court of Appeals for the Seventh Circuit · 1923
- Brenard Mfg. Co. v. MarcumCourt of Appeals of Tennessee · 1926
1 more not listed; retrieve them via the Exa API.