Natural Gas Pipeline Co. of America v. Federal Power Commission
Court of Appeals for the Seventh Circuit
1Opinion of the Court
LINDLEY, District Judge.
The original petitioners seek further exercise of the jurisdiction of this court in determination and distribution of the amounts payable by them, pursuant to and by virtue of the terms of the stay order entered and the bonds filed in the original proceeding and in restraint of suits in other forums.
On August 30, 1940, this court restrained temporarily, enforcement of the Federal Power Commission’s rate order of July 23, 1940, upon condition that petitioners file a bond in the sum of $1,000,000, conditioned as provided in the order. In November following, the court,…
2Cases cited28 opinions
- Federal Power Commission v. Natural Gas Pipeline Co.Supreme Court of the United States · 1942
- United States v. MorganSupreme Court of the United States · 1939
- Ford Motor Co. v. National Labor Relations BoardSupreme Court of the United States · 1939
- Gunter v. Atlantic Coast Line RailroadSupreme Court of the United States · 1906
- Krippendorf v. HydeSupreme Court of the United States · 1884
23 more not listed; retrieve them via the Exa API.
3Cited by23 opinions
- Mobil Oil Corp. v. Federal Power CommissionSupreme Court of the United States · 1974
- United States v. ManningDistrict Court, W.D. Louisiana · 1963
- Market Street Railway Co. v. Railroad CommissionCalifornia Supreme Court · 1946
- Sally Saunders Toles, Elyse Saunders Patterson and Sue Saunders Graham v. United StatesCourt of Appeals for the Tenth Circuit · 1967
- Sam Rayburn Dam Electric Cooperative v. Federal Power CommissionCourt of Appeals for the D.C. Circuit · 1975
18 more not listed; retrieve them via the Exa API.