Legal Opinion

Arrowhead Construction Co. v. Essex Corp.

Supreme Court of Kansas

Decided April 29, 1983No. 54,193PublishedCited by 30 opinions

1Opinion of the Court

The opinion of the court was delivered by

Herd, J.:

This is an action for breach of contract. The appeal is from the trial court’s order granting judgment on the counterclaims of Frank Crotts and Glenn Henley.

A contract for the construction of a low-income housing project in Lakin is the issue from which this case arose. The original contract for the project was let to Essex Corporation as the general contractor on March 15, 1978. On March 23, 1978, Essex acquired a “Labor and Material Payment Bond” from Inland Insurance Company and Universal Surety Company.

Essex subcontracted the job to…

2Cases cited10 opinions

  1. Augusta Bank & Trust v. BroomfieldSupreme Court of Kansas · 1982
  2. Steele v. HarrisonSupreme Court of Kansas · 1976
  3. International Petroleum Services, Inc. v. S & N Well Service, Inc.Supreme Court of Kansas · 1982
  4. Cosgrove v. YoungSupreme Court of Kansas · 1981
  5. Sidwell Oil & Gas Co. v. LoydSupreme Court of Kansas · 1981

5 more not listed; retrieve them via the Exa API.

3Cited by30 opinions

  1. I.M.A., Inc. v. Rocky Mountain Airways, Inc.Supreme Court of Colorado · 1986
  2. NEA-Coffeyville v. Unified School District No. 445Supreme Court of Kansas · 2000
  3. Miller v. BotwinSupreme Court of Kansas · 1995
  4. Scott v. StricklandCourt of Appeals of Kansas · 1984
  5. Lindsey Masonry Co. v. Murray & Sons Construction Co.Court of Appeals of Kansas · 2017

25 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API