Legal Opinion

Brown v. Scism

Court of Appeals of North Carolina

Decided February 17, 1981No. 8022SC558PublishedCited by 11 opinions

1Opinion of the Court

MARTIN (Harry C.), Judge.

The dispute between the parties in this case is whether defendant Seism was required to move dirt onto his portion of the project from outside its boundaries in order to fulfill his agreement under the contract. Defendant contends that he fully complied with the contract by moving all the yardage that could be moved within the boundaries of the contract. Plaintiff asserts in his brief that under the agreement defendant was required to complete all the grading work, which entailed three major operations:(1) removing dirt to cut the high areas or “cuts” down to the…

2Cases cited26 opinions

  1. Rose v. Vulcan Materials CompanySupreme Court of North Carolina · 1973
  2. Root v. Allstate Insurance CompanySupreme Court of North Carolina · 1968
  3. Crockett v. First Federal Savings & Loan Ass'n of CharlotteSupreme Court of North Carolina · 1976
  4. Jones v. Palace Realty Co.Supreme Court of North Carolina · 1946
  5. Gregory v. LynchSupreme Court of North Carolina · 1967

21 more not listed; retrieve them via the Exa API.

3Cited by11 opinions

  1. Maintenance Equipment Co., Inc. v. Godley BuildersCourt of Appeals of North Carolina · 1992
  2. Stan D. Bowles Distributing Co. v. Pabst Brewing Co.Court of Appeals of North Carolina · 1984
  3. Allen v. Roberts Const. Co., Inc.Court of Appeals of North Carolina · 2000
  4. Georgia-Pacific Corp. v. BondurantCourt of Appeals of North Carolina · 1986
  5. Murrow v. DanielsCourt of Appeals of North Carolina · 1987

6 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API