Appollo v. Reynolds
Court of Appeals of Minnesota
1Opinion of the Court
OPINION
LESLIE, Judge.
The buyers of several townhouses sued the sellers when they were unable to close on the dates specified in their respective purchase agreements, due to delays in construction. The .trial court awarded the buyers damages caused by the increase in interest rates between the time of the originally scheduled closings and the actual closing dates. The sellers have appealed. We affirm.
FACTS
In 1983 the respondents (“buyers”) each signed purchase agreements for townhouses built and sold by the appellants (“sellers”). The closing dates were specified in the agreements, and the…
2Cases cited12 opinions
- Stephenson v. Capano Development, Inc.Supreme Court of Delaware · 1983
- Dolder v. GriffinSupreme Court of Minnesota · 1982
- Bevan v. J.H. Construction Co.Utah Supreme Court · 1983
- Edelstein v. Duluth, Missabe & Iron Range Railway Co.Supreme Court of Minnesota · 1948
- Foust v. HansonCourt of Appeals of Texas · 1981
7 more not listed; retrieve them via the Exa API.
3Cited by10 opinions
- National Union Fire Insurance v. Schwing America, Inc.Court of Appeals of Minnesota · 1989
- Marriage of Cronin v. CroninCourt of Appeals of Minnesota · 1985
- Patterson v. StoverCourt of Appeals of Minnesota · 1987
- Steinhilber v. Prairie Pine Mutual Insurance Co.Court of Appeals of Minnesota · 1995
- Hanson v. MoellerCourt of Appeals of Minnesota · 1985
5 more not listed; retrieve them via the Exa API.