Plaintiff is the assignee of Nationwide Building Contractors, Inc. (Nationwide). On October 18,1974, defendant and Nationwide entered into a written contract under which Nationwide was to provide the labor and materials incident to the erection of a steel building according to certain specifications. The contract price was $29,140 payable in three installments. The first installment ($7,285) was paid by defendant on execution of the contract.

The building was only partially completed. Plaintiff sued for the balance of the contract price. The answer of defendant alleged, among other things,…

2Cases cited4 opinions

  1. Barber v. M. F. A. Milling Co.Missouri Court of Appeals · 1976
  2. Davis v. SchottMissouri Court of Appeals · 1974
  3. Wombles v. General American Life Insurance Co.Missouri Court of Appeals · 1976
  4. Stokes v. KellyMissouri Court of Appeals · 1976

3Cited by3 opinions

  1. Tripp v. HarrymanMissouri Court of Appeals · 1981
  2. Tudor v. TudorMissouri Court of Appeals · 1981
  3. Williford v. WhiteMissouri Court of Appeals · 1979

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API