State ex rel. General Electric Supply Co. v. Jordano Electric Co.
Ohio Supreme Court
1Opinion of the CourtWright, J.
The issue before us is whether CMHA is entitled to a setoff against the funds in escrow to remedy Jordano’s failure to perform its contract with CMHA. For the reasons that follow, we hold that CMHA is entitled to the setoff and the court of appeals correctly affirmed the trial court’s grant of partial summary judgment to CMHA.
To determine the rights of the parties we must examine the statutory scheme set out in R.C. Chapter 1311 concerning mechanics’ liens filed by subcontractors, materialmen, laborers, and mechanics on escrow payments to contractors on public projects. The pertinent statutes…
2Cases cited6 opinions
- Columbus-Suburban Coach Lines, Inc. v. Public Utilities CommissionOhio Supreme Court · 1969
- Lee Turzillo Contracting Co. v. Cincinnati Metropolitan Housing AuthorityOhio Supreme Court · 1967
- Clark & Co. v. ParkerSupreme Court of Iowa · 1882
- In re SchillingDistrict Court, N.D. Ohio · 1918
- Stone Post Co. v. CorcoranSupreme Court of New Jersey · 1910
1 more not listed; retrieve them via the Exa API.
3Cited by10 opinions
- Cline v. Ohio Bureau of Motor VehiclesOhio Supreme Court · 1991
- Gascho v. Global Fitness Holdings, LLCDistrict Court, S.D. Ohio · 2012
- Schumacher v. State Automobile Mutual InsuranceDistrict Court, S.D. Ohio · 2014
- State ex rel. Peregrine Health Servs. of Columbus, L.L.C. v. Sears, Dir., Ohio Dept. of MedicaidOhio Court of Appeals · 2020
- In Re Wm. Cargile Contractor, Inc.United States Bankruptcy Court, S.D. Ohio · 1993
5 more not listed; retrieve them via the Exa API.