Salem Building Supply Co. v. J.B.L. Construction Co.
Massachusetts Appeals Court
1Opinion of the CourtHale, C.J.
The plaintiff in this action was the supplier of dry wall and other materials to W. J. Martinoli, 2 a subcontractor on an apartment complex in Lincoln. The de fendants, J.B.L. Construction Co., Inc. (J.B.L.), the principal contractor, and United Pacific Insurance Company (United Pacific), as surety, executed a labor and material bond for the project. The plaintiff claims the right to recover under the bond for the unpaid balance of its account with Martinoli. Upon the plaintiff’s motion for summary judgment the judge entered judgment for the plaintiff in the amount of $46,881.39. After a…
2Cases cited15 opinions
- United States v. Diebold, Inc.Supreme Court of the United States · 1962
- Community National Bank v. DawesMassachusetts Supreme Judicial Court · 1976
- Stetson v. Board of Selectmen of CarlisleMassachusetts Supreme Judicial Court · 1976
- Hub Associates, Inc. v. GoodeMassachusetts Supreme Judicial Court · 1970
- Johnson-Foster Co. v. D'Amore Construction Co.Massachusetts Supreme Judicial Court · 1943
10 more not listed; retrieve them via the Exa API.
3Cited by19 opinions
- Shimer v. Foley, Hoag & Eliot LLPMassachusetts Appeals Court · 2003
- USTrust Co. v. KennedyMassachusetts Appeals Court · 1983
- Davidson Pipe Supply Co., Inc. v. JohnsonMassachusetts Appeals Court · 1982
- Helmes v. CommonwealthMassachusetts Supreme Judicial Court · 1990
- Brasi Development Corp. v. Attorney GeneralMassachusetts Supreme Judicial Court · 2010