Factory Realty Corp. v. Corbin-Holmes Shoe Co.
Massachusetts Supreme Judicial Court
1Opinion of the CourtDolan, J.
This is an action of contract to recover damages for the alleged breach of a covenant by the defendant contained in an instrument under seal which was executed by the parties. The case was referred to an auditor to determine the damages “in the event there should be liability.”
*326Material facts found by the auditor follow. On June 29, 1928, the parties executed the instrument in question which, in substance, provided for the lease and ultimate purchase of a factory building by the defendant from the plaintiff on a deferred payment plan, with the privilege of cancellation of the contract by the…
2Cases cited18 opinions
- Guerin v. StacyMassachusetts Supreme Judicial Court · 1900
- Fitzgerald v. AllenMassachusetts Supreme Judicial Court · 1880
- Rogers v. Rogers & BrotherMassachusetts Supreme Judicial Court · 1885
- Garst v. HarrisMassachusetts Supreme Judicial Court · 1900
- Shea v. Aetna Life InsuranceMassachusetts Supreme Judicial Court · 1935
13 more not listed; retrieve them via the Exa API.
3Cited by18 opinions
- NPS LLC v. Ambac Assurance Corp.District Court, D. Massachusetts · 2010
- Stern & Co. v. International Harvester Co.Supreme Court of Connecticut · 1961
- Bermingham v. ThomasMassachusetts Appeals Court · 1975
- Priestley v. Sharaf's, Inc.Massachusetts Appeals Court · 1976
- Morad v. RamosMassachusetts Supreme Judicial Court · 1953
13 more not listed; retrieve them via the Exa API.