Legal Opinion

Porter v. Eyer

Arizona Supreme Court

Decided February 21, 1956No. 5999PublishedCited by 30 opinions

1Opinion of the Court

UDALL, Justice.

The question is here presented whether a suit may be maintained by one who furnishes materials to a sub-contractor, against the prime contractor and his surety where there was no direct contractual relationship between said parties and neither the original contract with the owner nor the performance bond itself expressly provide for the maintenance of such a suit.

The undisputed facts are these: on January 27, 1953, defendant-appellant William S. Porter, a licensed contractor, agreed in writing with O. S. Stapley Company, a corporation, for a consideration of $39,100, to build a…

2Cases cited8 opinions

  1. American Federation of Labor v. American Sash & Door Co.Arizona Supreme Court · 1948
  2. Roberts v. SprayArizona Supreme Court · 1950
  3. Town of South Tucson v. Board of SupervisorsArizona Supreme Court · 1938
  4. Webb v. Crane Co.Arizona Supreme Court · 1938
  5. Baumann v. City of West AllisWisconsin Supreme Court · 1925

3 more not listed; retrieve them via the Exa API.

3Cited by30 opinions

  1. Employer's Liability Assurance Corporation v. LuntArizona Supreme Court · 1957
  2. Costanzo v. StewartCourt of Appeals of Arizona · 1969
  3. Arnold v. KnettleCourt of Appeals of Arizona · 1969
  4. Paul Schoonover, Inc. v. Ram Construction Inc.Arizona Supreme Court · 1981
  5. State v. JunkinCourt of Appeals of Arizona · 1979

25 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API